Here is my specific example. My scrum team has 3 qa people. There is one person who is the "qa-lead". But I feel they only use the title as a way to pass off all the work to myself and the other team member. The lead has a tendency to fill up their scrum board with what I think are mostly "fluff" story's/tasks. And delegates the "real" work.
Here are a couple examples of the "fluff" work:
- A testing task, that doesn't involve the lead doing any testing. The lead asks a person from another team to review a new feature. The team lead marks the task as QA Passed once the individual from the other team has reviewed it. But since the lead's name is on it, I feel it gives the impression that they did the testing.
- Carrying stories in their name for days in a row, and making no progress on them (I mean literally zero). These end up getting handed off to myself or the other team member at some point, and we have to start from scratch.
There are many other examples of "fluff" work. And I think they are organized so as to give the impression that they are constantly busy. I am not quite sure if I can raise this issue with my manager though.
I was curious if anyone has ever successfully navigated a situation like this? I've seen similar questions asked in the past but it seemed like the most common answer was "find a new job."
I wrote an answer on Stack Exchange about this (see link below), but Scrum tends to make everything about Scrum itself and all other actions begin to serve the sprint and not the project. When that happens, it becomes more important to look good according to Scrum than to actually get anything done (especially when the product owner/Scrum master are non-technical).
I know that in my job, people often judge me on the task board alone. It would not surprise me if something similar is happening in your company.
https://softwareengineering.stackexchange.com/questions/4104...
If you read some of the other answers to that question, there are numerous stories of developers using Scrum as a way to slack off.
I don't know what you can do about him as I suspect he is acting rather rationally. The fact that he can get away with this seems to indicate that overall productivity and work product do not really matter.
Put another way, some bad situations are not accidental. If you try to fix them, you become the problem in the eyes of those maintaining it.